Also known as: ITP, quality plan, inspection test plan.
Where NDT fits
NDT activities appear as lines in the fabricator’s or asset owner’s ITP: for example 100% VT of all welds, 10% RT of butt welds per ASME VIII UW-52, MPI of fillet welds per AWS D1.1. The inspection company’s reports are the records that close those lines.
ITPs in AMPS
An ITP scope becomes a set of jobs in AMPS, often in a job group, each producing its report from your Word template. The job statuses on the asset page show which lines are complete, in progress or not started.